Sump Pump Sizing
Wet-well volume, pump duty, discharge line and cycle-time check against Dubai Municipality guidelines and international plumbing-code baselines.
1Catchment & design storm
1Sewage inflow
2Pump configuration
3Wet well / pit
Basis of design
Every figure above is traceable to one of the sources below. Numbers marked DM come from current, published Dubai Municipality design guidelines; Intl. marks widely-used international plumbing-code / industry baselines used to fill gaps the Dubai guidelines leave open. Interpolated log-linearly between tabulated durations for any time-of-concentration not listed directly. DEWA regulates electricity and water connections in Dubai, and its published Green Building Regulations cover greywater reuse and discharge-quality rules — but no publicly indexed DEWA document sets sump-pit or sump-pump sizing criteria. The Dubai authority that actually publishes those criteria is Dubai Municipality (Sewerage Design Guidelines and Stormwater Design Guidelines, both dated 2025), so this tool cites DM directly rather than attributing sizing rules to DEWA. Confirm any DEWA-side approval or power-supply requirements for the pump room separately. Dubai Municipality, Sewerage Design Guidelines (24.01.25).Dubai IDF table (Dubai Municipality Stormwater Design Guidelines V2, Table 0-2) rainfall intensity, mm/hr
Why DEWA doesn’t appear in the calculations
Formulas & code clauses used
V = t·Q / 4 — DM Sewerage Design Guidelines §5.1.4 (24.01.25). Also documented internationally in US UFC EI 11C201 and standard lift-station design practice.Q = C·i·A / 360 (Q in m³/s, i in mm/hr, A in hectares) — standard international peak-runoff estimate.Sources
Dubai Municipality, Stormwater Design Guidelines V2.
DEWA, Green Building Regulations & Specifications (drainage/discharge quality only — no sump sizing content).
NYC Plumbing Code §712.3.2 and Chicago Plumbing Code §18-29-712 (IPC-family sump/ejector baseline).
Minnesota Rule 4715.2440 (UPC-derived duplex threshold, residential minimum storage).
US Unified Facilities Criteria EI 11C201, Table 7-1 (minimum pump cycle times, corroborating basis for V = tQ/4).